Technology Project Management Flashcards
7 cards from real DIS practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Technology Project Management flashcards as text
During a digital imaging lab upgrade, a stakeholder requests adding color calibration hardware after the project scope was finalized. This is best handled through:
Answer: A formal change control process
Formal change control ensures scope additions are evaluated for impact on budget, schedule, and resources before approval.
A project manager tracking a DIS lab rollout notices the CPI (Cost Performance Index) is 0.85. This indicates:
Answer: The project is receiving 85 cents of value for every dollar spent
A CPI below 1.0 means the project is over budget relative to work completed.
Which risk response strategy is most appropriate when a digital imaging project team decides to purchase insurance for equipment damage during transit?
Answer: Transfer
Transferring risk shifts the financial consequence of a risk event to a third party, such as an insurer.
A Gantt chart used in a digital imaging deployment project is primarily useful for:
Answer: Visualizing task durations and dependencies over time
Gantt charts display project tasks against a timeline, making schedule visualization intuitive.
When planning a multi-site digital imaging system rollout, the project manager uses a RACI matrix to:
Answer: Define roles and responsibilities for each task
A RACI matrix clarifies who is Responsible, Accountable, Consulted, and Informed for each project activity.
A digital imaging project is in execution when key team members resign unexpectedly. The project manager's first response should be to:
Answer: Assess impact on schedule and resource plan, then escalate
Assessing impact before acting ensures an informed response and proper communication to stakeholders.
The critical path in a project network diagram is defined as the sequence of tasks that:
Answer: Determines the shortest possible project duration
The critical path is the longest path through the project network, setting the minimum time to completion.