What is the difference between RPO and RTO in disaster recovery planning?
-
A
RPO is the recovery time objective, RTO is the recovery point objective
-
B
RPO defines maximum acceptable data loss measured in time; RTO defines maximum acceptable downtime before recovery must complete
-
C
RPO and RTO both measure downtime but in different units
-
D
RPO applies to databases while RTO applies to file systems