DCI Copper Installation 5 — Questions and Answers
Question 1: What is the minimum separation distance between copper data cables and electrical conduit carrying circuits of 2–5 kVA in open runs?
- 1 inch
- 2 inches
- 5 inches (Correct answer)
- 12 inches
Correct answer: 5 inches
ANSI/TIA-569 requires a minimum 5-inch (127 mm) separation between data cables and electrical conduit carrying 2–5 kVA to prevent EMI.
Question 2: What test verifies that each pair in a copper cable has approximately the same propagation delay?
- Propagation delay skew (Correct answer)
- Insertion loss
- Return loss
- ELFEXT
Correct answer: Propagation delay skew
Propagation delay skew measures the difference in signal travel time between the fastest and slowest pairs, which must be within 45 ns for Cat6/6A.
Question 3: A technician is pulling Category 6A cable in a conduit. The conduit fill is already at 40%. What should the technician do?
- Pull the cable anyway since 40% fill is acceptable
- Install a larger conduit or a parallel conduit run (Correct answer)
- Remove existing cables and re-bundle them tighter
- Use Cat6 instead, which has a smaller diameter
Correct answer: Install a larger conduit or a parallel conduit run
NEC and TIA-569 limit conduit fill to allow cable pulling without damage; at 40% fill adding more cable would exceed limits and risk damaging all cables.
Question 4: When testing a newly installed copper link, a 'FAIL – Return Loss' result most likely indicates what problem?
- A cable that is too long
- Impedance discontinuities caused by kinks, tight bends, or bad terminations (Correct answer)
- Incorrect T568A/B wiring standard selection
- A missing pair in the cable
Correct answer: Impedance discontinuities caused by kinks, tight bends, or bad terminations
Return loss failures are caused by impedance discontinuities in the cable path, such as kinks, excessively tight bends, over-tightened cable ties, or poor terminations.
Question 5: What is the function of a gel-filled splice case in copper outside plant (OSP) installations?
- To amplify signal strength over long runs
- To protect copper splice joints from moisture ingress (Correct answer)
- To convert copper to fiber at a cross-connect point
- To ground the cable shield to the building steel
Correct answer: To protect copper splice joints from moisture ingress
Gel-filled splice cases enclose and seal copper cable splices in outdoor environments, preventing water intrusion that would degrade performance or cause shorts.
Question 6: Which measurement parameter is used to evaluate the performance of a cable from end to end, combining both NEXT and attenuation?
- Return loss
- ACR-N (Attenuation to Crosstalk Ratio, Near-End) (Correct answer)
- Propagation delay skew
- DC loop resistance
Correct answer: ACR-N (Attenuation to Crosstalk Ratio, Near-End)
ACR-N (formerly called ACR) is calculated as NEXT minus insertion loss and represents the signal-to-noise ratio at the near end of the link.
Question 7: What is the correct method to handle excess cable slack at a work area outlet?
- Coil it tightly behind the outlet box
- Store it in a service loop with a diameter no less than 8 times the cable OD (Correct answer)
- Cut it flush with the back of the outlet box
- Fold it in half and staple it to the stud
Correct answer: Store it in a service loop with a diameter no less than 8 times the cable OD
Excess cable should be stored as a service loop with a minimum diameter of 8 times the cable's outer diameter to avoid exceeding the minimum bend radius.
What is the minimum separation distance between copper data cables and electrical conduit carrying circuits of 2–5 kVA in open runs?