What role does the design-build entity's contingency serve in a GMP contract?
Select your answer
A
It covers the owner's change orders only
B
It provides a buffer for unforeseen costs within the design-builder's scope that keeps the project within the GMP
C
It replaces the need for performance bonding
D
It is refunded to the owner at project completion