Which factor most strongly favors selecting design-build over design-bid-build when an owner has a fixed opening date?
Answer: Overlapping design and construction phases reduces overall schedule
Design-build enables concurrent design and construction, compressing the schedule compared to sequential design-bid-build delivery.
An owner wants maximum control over material specifications and design details throughout construction. Which delivery method best supports this goal?
Answer: Design-bid-build
Design-bid-build gives owners direct contractual authority over the designer, allowing ongoing specification changes without renegotiating a single entity's contract.
Under the DBIA framework, what term describes the situation where a single entity holds contractual responsibility for both design and construction?
Answer: Single-point accountability
Single-point accountability means the design-builder is the sole party contractually responsible to the owner for both design defects and construction defects.
A municipality needs a water treatment plant but lacks the internal expertise to develop detailed technical requirements. Which project delivery approach is most appropriate?
Answer: Performance-based design-build specifying outcomes rather than prescriptive design
Performance-based design-build lets owners define what the facility must accomplish, allowing the design-builder to innovate on how to achieve those outcomes.
Which procurement characteristic distinguishes qualifications-based selection (QBS) from low-bid selection in design-build?
Answer: QBS awards based on the team's experience and technical approach before price negotiation
QBS evaluates a firm's qualifications, past performance, and technical approach first, with price negotiated after the best-qualified team is identified.
When comparing risk allocation, how does design-build differ from design-bid-build regarding design errors discovered during construction?
Answer: In design-build, the design-builder bears the cost of correcting design errors without additional owner payment
Because the design-builder holds both contracts, design errors are the design-builder's responsibility to correct at no added cost to the owner.
An owner selects a project delivery method early in planning. Which DBIA-recognized benefit makes design-build particularly valuable when the project scope is not fully defined?
Answer: Progressive design-build allows scope to be refined collaboratively as design advances
Progressive design-build is structured so the owner and design-builder refine scope and price incrementally, making it well-suited to projects with evolving requirements.