Procuring Design-Build Services Flashcards
7 cards from real DBIA practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Procuring Design-Build Services flashcards as text
In a Best-Value procurement, which factor most directly distinguishes it from a low-bid selection?
Answer: Award considers both price and qualitative factors such as team qualifications and technical approach
Best-Value selection weighs qualitative factors (qualifications, technical approach, past performance) alongside price rather than awarding on price alone.
What is the primary purpose of an industry review (or 'industry forum') conducted before issuing an RFP?
Answer: To allow owners to gather market feedback and refine procurement documents before release
Industry forums allow owners to present draft procurement documents to potential proposers, gather feedback, and improve document quality before formal release.
Under DBIA best practices, which document type is typically released first in a two-phase design-build procurement?
Answer: Request for Qualifications (RFQ)
In two-phase procurement, an RFQ is issued first to establish a shortlist of qualified teams before the full RFP is released to those firms.
A design-build RFP that specifies performance criteria rather than prescriptive specifications primarily benefits the owner by:
Answer: Allowing design-builders to innovate and propose solutions that best meet project goals
Performance-based criteria encourage innovation by allowing design-builders to propose optimal solutions rather than prescribing a single design approach.
Which of the following best describes a 'stipend' in design-build procurement?
Answer: Compensation paid to unsuccessful shortlisted proposers to offset proposal development costs
Stipends are payments made to unsuccessful shortlisted proposers to partially offset their proposal preparation costs and encourage high-quality submissions.
When an owner uses a Qualifications-Based Selection (QBS) for design-build, price negotiation occurs:
Answer: After the most qualified firm is selected
In QBS, the owner selects the most qualified firm first and then negotiates a fair and reasonable price, similar to the Brooks Act model for A/E services.
Which contract provision is most important for defining the design-builder's obligation when the owner's RFP contains conflicting performance requirements?
Answer: An order of precedence clause
An order of precedence clause establishes which contract document governs when conflicts exist between the RFP, proposals, drawings, and specifications.