Design-Build Contracting Approaches Flashcards

7 cards from real DBIA practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Design-Build Contracting Approaches flashcards as text
  1. Which of the following best describes the 'turnkey' design-build contracting approach?

    Answer: The design-builder delivers a fully complete, operational facility ready for immediate owner use

    A turnkey contract obligates the design-builder to deliver a project fully complete and ready to operate, so the owner simply 'turns the key' to begin use.

  2. In design-build RFP development, the 'technical proposal' typically includes all of the following EXCEPT:

    Answer: Final lump sum contract price

    The final lump sum price is submitted in a separate price proposal, keeping technical evaluation independent from cost in a best-value selection process.

  3. A design-build contract provision requiring the design-builder to guarantee a specific energy consumption level is an example of:

    Answer: A performance specification

    Performance specifications define outcomes the completed project must achieve (such as energy use intensity targets) rather than dictating how to achieve them.

  4. In federal design-build procurement under FAR Part 36, the two-phase selection process Phase 1 is used to:

    Answer: Shortlist qualified offerors before requesting full technical proposals in Phase 2

    FAR 36.3 two-phase design-build selection uses Phase 1 to evaluate qualifications and shortlist typically three to five firms invited to submit full proposals in Phase 2.

  5. When a design-build owner provides an Allowance in the contract, it is most appropriate for:

    Answer: Scope items that cannot be fully defined at contract award but must be included in the contract

    Allowances reserve funds within the contract for undefined scope elements, with actual costs determined and credited or debited as work is defined and performed.

  6. Which risk is MOST appropriately retained by the owner in a design-build contract?

    Answer: Changes in applicable law after contract execution

    Changes in law after contract execution are typically owner risk because neither party can predict or control regulatory changes that affect project cost or design.

  7. The primary purpose of a 'design assist' subcontract in design-build is to:

    Answer: Allow specialty subcontractors to complete design for systems they will also install

    Design assist engages specialty subcontractors (e.g., mechanical, electrical) early to provide constructability input and develop installation-level design for their scopes.