  1. In best-value design-build selection, the 'adjusted score' method works by:

    Answer: Dividing the technical score by the price to identify the best value per dollar

    The adjusted score method divides a proposer's technical score by their price, selecting the team that offers the highest technical quality per dollar spent.

  2. A 'developer finance' design-build model is most commonly used when:

    Answer: Private developers finance, design, build, and sometimes operate a facility for a public owner

    Developer finance design-build (often called DBFOM or P3) involves private entities providing capital and taking on long-term project risk in exchange for future revenue or payments.

  3. Which clause in a design-build contract allocates risk for unforeseen subsurface conditions to the owner?

    Answer: Differing site conditions clause

    A differing site conditions clause shifts the risk of unexpected subsurface conditions back to the owner, preventing design-builders from inflating bids to cover that uncertainty.

  4. The DBIA standard form contract addresses design professional liability primarily by:

    Answer: Requiring the design-builder to carry errors and omissions insurance

    DBIA contract documents require the design-builder to maintain professional liability (errors and omissions) insurance to cover design-related claims.

  5. In a progressive design-build delivery, when is the contract price typically finalized?

    Answer: After the design reaches a defined milestone sufficient for accurate pricing

    Progressive design-build allows price to be established collaboratively as design advances to a level of completeness that enables reliable cost estimating.

  6. Which design-build project delivery characteristic most directly reduces schedule duration compared to design-bid-build?

    Answer: Ability to overlap design and construction phases (fast-tracking)

    Design-build enables fast-tracking by allowing construction of completed design packages to begin while design of later packages continues in parallel.

  7. Under the DBIA framework, 'owner's criteria' documents serve primarily to:

    Answer: Define the owner's performance requirements, standards, and constraints for the design-builder to meet

    Owner's criteria establish what outcomes and standards the project must achieve, giving the design-builder flexibility in how to meet those requirements.