Under FDOT Final Estimates, what is a 'Pay Item Allowance'?
-
A
A fixed-price budget item for work where the exact scope or quantity is unknown at bid time
-
B
An automatic 10% markup added to all labor costs
-
C
A payment reduction for substandard materials
-
D
A contractor bonus for completing an item ahead of schedule