Under FDOT Final Estimates, what action must be taken when measured quantities exceed the original contract quantity by more than 25%?
-
A
The excess quantity is automatically paid at the original unit price
-
B
A price adjustment or renegotiation may be required for the excess quantity above the threshold
-
C
The contractor must absorb the additional costs with no extra payment
-
D
The project is automatically terminated