What does 'form stripping time' or 'form removal time' mean in concrete bridge construction?
-
A
The time required to erect the formwork system
-
B
The minimum time after concrete placement that forms can be removed based on concrete strength
-
C
The time allotted to inspect forms before concrete is placed
-
D
The allowable time between form reuse applications