What is the primary distinction between Quality Control (QC) and Quality Assurance (QA) on FDOT construction projects?
-
A
QC uses more advanced testing equipment than QA
-
B
QC is the contractor's process for verifying their own work meets specs; QA is FDOT's independent verification that the QC process is working
-
C
QC focuses only on materials testing; QA covers workmanship and processes
-
D
QA is required only on federally funded projects while QC applies to all FDOT projects