During drilled shaft excavation using the wet method, what is the PRIMARY purpose of maintaining drilling slurry in the borehole?
-
A
To provide hydrostatic pressure that prevents the borehole walls from caving in
-
B
To lubricate the drill tooling for faster penetration
-
C
To carry drill cuttings to the surface for gradation testing
-
D
To cool the drill bit and prevent overheating