CST Sprint Planning & Sprint Review 3 — Questions and Answers
Question 1: A Scrum Team consistently fails to complete all Sprint Backlog items by the end of each Sprint. As a CST, what is the most important thing to examine first?
- Whether the Scrum Master is enforcing daily standups strictly
- Whether the team's Sprint forecasts are realistic relative to their actual velocity (Correct answer)
- Whether the Product Owner is attending Sprint Planning
- Whether stakeholders are providing timely feedback during the Sprint
Correct answer: Whether the team's Sprint forecasts are realistic relative to their actual velocity
Persistent incomplete Sprints usually signal overcommitment, so examining forecast accuracy against historical velocity is the highest-priority diagnosis.
Question 2: Which outcome is the primary purpose of Sprint Planning?
- A signed commitment from the Development Team to deliver all selected items
- A shared understanding of the Sprint Goal and a plan for the first days of work (Correct answer)
- A detailed project plan approved by the Product Owner and Scrum Master
- An updated release roadmap reflecting the new Sprint's deliverables
Correct answer: A shared understanding of the Sprint Goal and a plan for the first days of work
Sprint Planning produces a Sprint Goal, a set of selected backlog items, and an initial plan—not a binding contract.
Question 3: The Sprint Review reveals that the Increment does not meet stakeholders' expectations despite meeting all acceptance criteria. What does this most likely indicate?
- The Scrum Master failed to facilitate the Sprint Review correctly
- The acceptance criteria did not fully capture stakeholder needs—a Product Backlog refinement gap (Correct answer)
- The Development Team should have worked overtime to exceed the criteria
- Sprint Reviews should be eliminated in favor of more frequent demos
Correct answer: The acceptance criteria did not fully capture stakeholder needs—a Product Backlog refinement gap
A gap between met criteria and stakeholder satisfaction points to incomplete or misaligned acceptance criteria that should be improved through better refinement.
Question 4: How should a Scrum Team handle a Sprint Goal that becomes obsolete midway through a Sprint due to a sudden market change?
- Continue the Sprint regardless; abandon only at Sprint boundary
- The Product Owner may cancel the Sprint if the goal no longer has value (Correct answer)
- The Scrum Master cancels the Sprint after consulting the Development Team
- The team selects a new Sprint Goal and continues without cancellation
Correct answer: The Product Owner may cancel the Sprint if the goal no longer has value
Only the Product Owner has the authority to cancel a Sprint when the Sprint Goal is rendered obsolete.
Question 5: During a Sprint Review, the Development Team demonstrates a feature and the Product Owner says it is 'Done.' Two days later a critical bug is found. What should happen?
- The Sprint is retroactively marked as failed
- A new Product Backlog Item is created to address the bug in a future Sprint (Correct answer)
- The Development Team must fix the bug before the next Sprint Review
- The Scrum Master decides whether to roll back the release
Correct answer: A new Product Backlog Item is created to address the bug in a future Sprint
Bugs discovered after a Sprint are handled as new Product Backlog Items, prioritized by the Product Owner for a future Sprint.
Question 6: What is the Scrum Team's primary input when forecasting how much work to select during Sprint Planning?
- The project manager's capacity estimate for the team
- The team's past performance (velocity) and current capacity (Correct answer)
- The Product Owner's preferred delivery date for the release
- The number of Product Backlog Items ready in the top of the backlog
Correct answer: The team's past performance (velocity) and current capacity
Past velocity combined with the team's current capacity (accounting for holidays, absences, etc.) provides the most reliable basis for forecasting.
Question 7: A stakeholder not invited to the Sprint Review contacts the Scrum Master asking for the demo recording. How should the Scrum Master respond?
- Refuse access to protect team privacy
- Coordinate with the Product Owner, who decides how to share Sprint Review outcomes (Correct answer)
- Share the recording directly, as transparency is a Scrum value
- Require the stakeholder to attend in person next Sprint
Correct answer: Coordinate with the Product Owner, who decides how to share Sprint Review outcomes
The Product Owner is accountable for stakeholder engagement and should decide how Sprint Review information is disseminated.
A Scrum Team consistently fails to complete all Sprint Backlog items by the end of each Sprint.
As a CST, what is the most important thing to examine first?