CST Software & Tools for Scheduling 2 — Questions and Answers
Question 1: In Primavera P6, what is the purpose of the 'Activity Step' feature?
- To break an activity into smaller trackable sub-tasks (Correct answer)
- To add float to a critical path activity
- To link activities across project hierarchies
- To set baseline dates for the WBS
Correct answer: To break an activity into smaller trackable sub-tasks
Activity Steps allow schedulers to track incremental progress within a single activity without creating separate schedule activities.
Question 2: Which Microsoft Project view displays resource allocation across time in a bar-chart format?
- Network Diagram
- Resource Usage
- Gantt Chart
- Resource Graph (Correct answer)
Correct answer: Resource Graph
The Resource Graph view shows resource allocation levels over time using a histogram-style bar chart.
Question 3: What does the 'Leveling Delay' field represent in Microsoft Project after resource leveling?
- The amount of lag added between linked tasks
- The delay added to a task to resolve a resource overallocation (Correct answer)
- The difference between early and late start dates
- The total float consumed by a resource
Correct answer: The delay added to a task to resolve a resource overallocation
Leveling Delay is the amount of time Microsoft Project delays a task's start to resolve a resource overallocation.
Question 4: In scheduling software, what is a 'resource calendar' used for?
- Tracking project milestones
- Defining when a specific resource is available to work (Correct answer)
- Setting the project's working days globally
- Calculating earned value metrics
Correct answer: Defining when a specific resource is available to work
A resource calendar defines the working times and non-working exceptions for an individual resource, which may differ from the project calendar.
Question 5: Which Primavera P6 feature allows you to compare the current schedule against a previously saved schedule?
- Schedule Check
- Claim Digger (Correct answer)
- Risk Register
- WBS Comparison Tool
Correct answer: Claim Digger
Claim Digger is a Primavera P6 utility that compares two schedule versions and produces a report of differences in activity dates, relationships, and durations.
Question 6: In Microsoft Project, what effect does setting a task's constraint to 'As Late As Possible' have in a forward-scheduled project?
- The task is placed at the end of its available float window (Correct answer)
- The task is pinned to the project start date
- The task becomes a milestone with zero duration
- The task is removed from the critical path
Correct answer: The task is placed at the end of its available float window
ALAP schedules the task as late as possible within its dependency chain, consuming all available float.
Question 7: What is the primary advantage of using a cloud-based scheduling tool over a desktop-installed application?
- Higher calculation accuracy for CPM
- Real-time multi-user collaboration without file sharing (Correct answer)
- Automatic integration with all ERP systems
- Unlimited number of activities per project
Correct answer: Real-time multi-user collaboration without file sharing
Cloud-based tools enable multiple stakeholders to view and update the schedule simultaneously without emailing files or managing version conflicts.
In Primavera P6, what is the purpose of the 'Activity Step' feature?