CST Baseline & Earned Value Schedule 3 — Questions and Answers
Question 1: Which method of measuring earned value assigns 100% credit only when an activity is fully completed?
- Weighted milestones
- Percent complete
- 0/100 rule (Correct answer)
- 50/50 rule
Correct answer: 0/100 rule
The 0/100 rule assigns 0% earned value when work starts and 100% only upon full completion, eliminating partial credit.
Question 2: What does the To-Complete Performance Index (TCPI) represent?
- The cost efficiency achieved to date
- The required cost efficiency to complete remaining work within budget (Correct answer)
- The ratio of budgeted to actual costs
- The percentage of work completed
Correct answer: The required cost efficiency to complete remaining work within budget
TCPI = (BAC - EV) / (BAC - AC), indicating the cost efficiency required for remaining work to meet the BAC.
Question 3: When a project baseline is established, the time-phased budget for each control account is called what?
- Work Breakdown Structure element
- Control Account Plan budget
- Budget at Completion (Correct answer)
- Performance Measurement Baseline spread
Correct answer: Budget at Completion
BAC (Budget at Completion) represents the total authorized budget for each control account or the entire project in the baseline.
Question 4: A project shows CPI = 1.2 and SPI = 0.9. Which statement best describes this situation?
- The project is over budget and ahead of schedule
- The project is under budget but behind schedule (Correct answer)
- The project is on budget and on schedule
- The project is over budget and behind schedule
Correct answer: The project is under budget but behind schedule
CPI > 1.0 means under budget (cost efficient), while SPI < 1.0 means behind schedule.
Question 5: In the context of schedule baselines, what is a 'baseline deviation'?
- A formal change approved through change control
- The difference between current schedule dates and the approved baseline dates (Correct answer)
- A risk response plan for schedule overruns
- An update to the resource allocation plan
Correct answer: The difference between current schedule dates and the approved baseline dates
A baseline deviation is the measured difference between the approved baseline dates and the current forecast or actual dates.
Question 6: Which earned value technique is most appropriate for long-duration, continuous activities with no distinct milestones?
- 0/100 rule
- Apportioned effort
- Level of effort (LOE) (Correct answer)
- Weighted milestones
Correct answer: Level of effort (LOE)
Level of Effort (LOE) is used for support or ongoing activities whose value is measured purely by time elapsed rather than discrete deliverables.
Question 7: What is the primary purpose of establishing a schedule baseline before project execution begins?
- To assign resource leveling constraints
- To provide a fixed reference point for measuring schedule performance (Correct answer)
- To finalize procurement contracts
- To define the project charter
Correct answer: To provide a fixed reference point for measuring schedule performance
The schedule baseline serves as the approved reference against which actual progress is compared to calculate schedule variances.
Which method of measuring earned value assigns 100% credit only when an activity is fully completed?