CST CST Schedule Risk & Contingency Analysis 2 — Questions and Answers
Question 1: What AACE International recommended practice provides guidance on schedule risk analysis?
- AACE RP 57R-09 (Correct answer)
- AACE RP 10S-90
- AACE RP 18R-97
- AACE RP 29R-03
Correct answer: AACE RP 57R-09
AACE RP 57R-09 provides a framework for integrated cost and schedule risk analysis, including Monte Carlo simulation methods for project schedules.
Question 2: In schedule risk analysis, what does a 'three-point estimate' consist of?
- Optimistic, most likely, and pessimistic duration estimates for an activity (Correct answer)
- Early start, planned start, and late start dates
- Minimum, average, and maximum resource units
- Best case, base case, and worst case cost estimates
Correct answer: Optimistic, most likely, and pessimistic duration estimates for an activity
A three-point estimate uses optimistic (O), most likely (M), and pessimistic (P) durations to model activity duration uncertainty for risk analysis.
Question 3: What is schedule risk exposure?
- The product of the probability of a risk event occurring and its schedule impact in days (Correct answer)
- The total number of risks identified in the risk register
- The difference between the planned and actual completion date
- The sum of all float across the project network
Correct answer: The product of the probability of a risk event occurring and its schedule impact in days
Schedule risk exposure quantifies the expected schedule impact of a risk by multiplying its probability of occurrence by the number of days of delay it would cause.
Question 4: Which technique involves deliberately planning workarounds in advance for risks that have high probability and high schedule impact?
- Contingency planning (Correct answer)
- Risk acceptance
- Risk escalation
- Residual risk monitoring
Correct answer: Contingency planning
Contingency planning creates predefined response strategies (workarounds) for high-probability, high-impact risks so that the team can react quickly if those risks materialize.
Question 5: In a Monte Carlo schedule simulation, what does a wider spread in the S-curve output indicate?
- Greater uncertainty and risk in the schedule (Correct answer)
- A more detailed and accurate schedule
- Fewer activities on the critical path
- Better resource allocation
Correct answer: Greater uncertainty and risk in the schedule
A wider S-curve spread in Monte Carlo output indicates that the range of possible completion dates is large, reflecting higher schedule uncertainty and risk.
Question 6: What is the purpose of a 'risk register' in schedule risk management?
- To document identified risks, their probability, impact, and response strategies (Correct answer)
- To track actual schedule performance against baseline
- To record all schedule changes and revisions
- To list all project milestones and their owners
Correct answer: To document identified risks, their probability, impact, and response strategies
The risk register is a project document that captures all identified risks along with their probability, potential schedule impact, and planned mitigation or contingency responses.
What AACE International recommended practice provides guidance on schedule risk analysis?