During a risk evaluation, a supervisor identifies a threat but determines that the cost of the countermeasure exceeds the value of the asset at risk. The MOST appropriate risk response is to:
-
A
Reduce the risk through partial countermeasures
-
B
Transfer the risk to an insurer
-
C
Accept the risk and document the decision
-
D
Eliminate the asset entirely