A Product Owner notices that the same stakeholders always dominate Sprint Review discussions, while others remain silent. What should the Product Owner do?
-
A
Allow dominant stakeholders to lead as they are the most engaged
-
B
Actively facilitate the review to ensure diverse stakeholder voices are heard
-
C
Remove quiet stakeholders from future Sprint Reviews
-
D
Have the Scrum Master send surveys to silent stakeholders afterward