A Product Owner discovers that two key stakeholders have conflicting priorities for the next Sprint. What is the BEST course of action?
-
A
Escalate the conflict to the Scrum Master to resolve
-
B
Facilitate a conversation between stakeholders to reach alignment before Sprint Planning
-
C
Split the Sprint into two tracks to satisfy both stakeholders
-
D
Let the Development Team decide which priority to follow