A new Product Owner joins a team and finds the Product Backlog has 300 items with no clear ordering. What should they do FIRST?
-
A
Delete all items older than six months to reduce clutter
-
B
Immediately order the backlog by the volume of stakeholder requests each item received
-
C
Engage stakeholders and the Development Team to understand value and dependencies, then begin ordering by priority
-
D
Ask the Scrum Master to order the backlog since they have the most team knowledge