A stakeholder demands a feature be added immediately to the current Sprint. What should the Product Owner do?
-
A
Add it to the Sprint Backlog immediately
-
B
Evaluate it, prioritize it in the Product Backlog, and address it in a future Sprint
-
C
Ask the Development Team to extend the Sprint
-
D
Reject it outright without discussion