A Product Owner discovers that a high-priority feature will take three Sprints to complete. What is the BEST approach?
-
A
Delay the feature until capacity allows it in one Sprint
-
B
Break the feature into smaller deliverable increments across Sprints
-
C
Ask the Scrum Master to extend the Sprint length
-
D
Remove lower-priority items from the backlog permanently