A Product Owner discovers that a recently completed Product Backlog item does not meet stakeholder expectations. What is the best course of action?
-
A
Reopen the item in the current Sprint
-
B
Create a new Product Backlog item to address the gap and prioritize accordingly
-
C
Blame the Development Team for misunderstanding the requirement
-
D
Ignore it until the next release