A security project manager is determining the critical path for an IDS deployment. What does identifying the critical path allow the manager to do?
-
A
Allocate the entire budget to high-priority tasks
-
B
Identify tasks where delays will directly delay the project finish date
-
C
Remove all float from non-critical activities
-
D
Reassign resources from non-security tasks