A security project manager uses Estimate at Completion (EAC) to forecast final project cost. If the CPI is 0.90 and Budget at Completion (BAC) is $500,000, what is the EAC (assuming current performance continues)?
-
A
$450,000
-
B
$555,556
-
C
$500,000
-
D
$510,000