A security project is implementing multi-factor authentication (MFA) across 5,000 endpoints. Progress monitoring reveals 30% adoption after 60% of the timeline has elapsed. What should the project manager assess first?
-
A
Whether to cancel the project
-
B
Schedule variance and its root cause to determine corrective action
-
C
Whether to reduce the MFA rollout scope permanently
-
D
Whether stakeholders are satisfied with current adoption