What is the primary purpose of an Integrated Change Control process in project management?
-
A
To document all project changes after they are implemented
-
B
To review, approve, or reject change requests and manage changes throughout the project lifecycle
-
C
To assign change ownership to functional managers
-
D
To communicate change impact exclusively to the project sponsor