Which communication model is most appropriate when a senior project manager needs to present complex project data to a non-technical executive board?
-
A
Bottom-up detailed reporting
-
B
Tailored executive summary with visual dashboards
-
C
Technical specification documents
-
D
Verbal-only briefings with no documentation