A senior project manager identifies a key executive stakeholder who is disengaged from the project. What is the BEST first step?
-
A
Conduct a one-on-one meeting to understand their concerns and interests
-
B
Send weekly status reports and wait for feedback
-
C
Escalate the issue to the project sponsor immediately
-
D
Remove the stakeholder from communications to reduce noise