A senior PM is presenting project status to an executive board. Which communication style is MOST appropriate?
-
A
Detailed technical walk-through of all workstreams
-
B
High-level summary focused on milestones, risks, and decisions needed
-
C
Comprehensive Gantt chart review
-
D
Team-level task completion percentages