CSM Stormwater Regulations & Compliance 2 — Questions and Answers
Question 1: Under the Clean Water Act Section 402, which permit program directly authorizes the discharge of stormwater to waters of the US?
- Section 404 Dredge and Fill Permit
- NPDES Permit Program (Correct answer)
- Safe Drinking Water Act Underground Injection Program
- Resource Conservation and Recovery Act Permit
Correct answer: NPDES Permit Program
The National Pollutant Discharge Elimination System (NPDES) under CWA Section 402 is the primary permitting mechanism for stormwater discharges.
Question 2: A construction site disturbing 0.8 acres that is part of a larger common plan of development that will disturb 1.5 acres total — does it require a Construction General Permit?
- No, because the individual site is under 1 acre
- Yes, because the common plan of development exceeds 1 acre (Correct answer)
- Only if the site discharges directly to an impaired water body
- Only if the owner has had a prior permit violation
Correct answer: Yes, because the common plan of development exceeds 1 acre
EPA's CGP triggers apply to the entire common plan of development or sale, so if the overall plan disturbs ≥1 acre the permit is required regardless of individual lot size.
Question 3: Which EPA Phase II rule first extended NPDES stormwater permit requirements to small MS4s?
- 1990 Phase I Rule
- 1999 Phase II Final Rule (Correct answer)
- 2010 Small MS4 Rule
- 2016 WOTUS Rule
Correct answer: 1999 Phase II Final Rule
The 1999 Phase II Final Rule (effective March 2003) expanded NPDES coverage to small MS4s in urbanized areas and smaller construction sites.
Question 4: What is the primary purpose of a Stormwater Pollution Prevention Plan (SWPPP) at an industrial facility?
- Replace the requirement for a NPDES permit
- Document BMPs to prevent pollutants from entering stormwater discharges (Correct answer)
- Establish water quality trading credits
- Satisfy state floodplain management requirements
Correct answer: Document BMPs to prevent pollutants from entering stormwater discharges
A SWPPP identifies potential pollutant sources and describes BMPs to prevent pollutants from reaching stormwater runoff.
Question 5: Under the MS4 program, which of the six minimum control measures addresses removing floatables and debris from stormwater before it enters receiving waters?
- Illicit Discharge Detection and Elimination
- Post-Construction Stormwater Management
- Pollution Prevention/Good Housekeeping (Correct answer)
- Construction Site Stormwater Runoff Control
Correct answer: Pollution Prevention/Good Housekeeping
Pollution Prevention/Good Housekeeping covers practices at municipal operations that prevent pollutant introduction, including debris management.
Question 6: A state issues a General Permit for industrial stormwater that is more stringent than the EPA baseline MSGP. Which statement is correct?
- The facility must only comply with the federal baseline
- States may not exceed federal requirements for stormwater
- The facility must comply with the more stringent state requirements (Correct answer)
- The facility may choose whichever standard it prefers
Correct answer: The facility must comply with the more stringent state requirements
Under the Clean Water Act's anti-degradation framework, states may set standards more stringent than federal requirements, and facilities must comply with the stricter standard.
Question 7: Which enforcement mechanism allows EPA to issue an immediate order requiring a party to cease discharging without going to court first?
- Consent Decree
- Administrative Compliance Order (Correct answer)
- Citizen Suit
- Notice of Violation
Correct answer: Administrative Compliance Order
EPA's Administrative Compliance Orders under CWA Section 309(a) can require immediate cessation of violations without prior judicial action.
Under the Clean Water Act Section 402, which permit program directly authorizes the discharge of stormwater to waters of the US?