CSM Project Management Fundamentals 2 — Questions and Answers
Question 1: Which document formally authorizes a project and grants the project manager authority to apply organizational resources?
- Project Management Plan
- Project Charter (Correct answer)
- Statement of Work
- Business Case
Correct answer: Project Charter
The Project Charter formally authorizes the project and gives the project manager authority to use organizational resources.
Question 2: In the context of project scheduling, what is a 'milestone'?
- A task with the longest duration on the critical path
- A significant point or event in the project with zero duration (Correct answer)
- A summary task that groups related activities
- A resource-leveling checkpoint
Correct answer: A significant point or event in the project with zero duration
A milestone is a significant event or point in the project schedule with zero duration, used to mark key deliverables or decision points.
Question 3: Which conflict resolution technique is considered the most effective for achieving long-term resolution?
- Smoothing
- Forcing
- Compromising
- Collaborating (Problem Solving) (Correct answer)
Correct answer: Collaborating (Problem Solving)
Collaborating or problem solving addresses the root cause of conflict and leads to a win-win outcome, making it the most effective long-term resolution technique.
Question 4: A project manager notices that actual costs are running higher than planned but work is being completed faster than scheduled. Which EVM indicators reflect this scenario?
- CPI > 1, SPI < 1
- CPI < 1, SPI > 1 (Correct answer)
- CPI < 1, SPI < 1
- CPI > 1, SPI > 1
Correct answer: CPI < 1, SPI > 1
CPI < 1 indicates cost overrun (spending more than planned) and SPI > 1 indicates schedule efficiency (completing work faster than planned).
Question 5: What is the primary purpose of a Work Breakdown Structure (WBS)?
- To assign resources to project tasks
- To decompose project scope into manageable work packages (Correct answer)
- To create a sequenced schedule of activities
- To document project risks and mitigation plans
Correct answer: To decompose project scope into manageable work packages
The WBS decomposes the total project scope into smaller, more manageable components called work packages.
Question 6: Which type of project organizational structure gives the project manager the MOST authority?
- Functional
- Weak Matrix
- Balanced Matrix
- Projectized (Correct answer)
Correct answer: Projectized
In a projectized organization, the project manager has full authority and team members report directly to them.
Question 7: During project execution, a key stakeholder requests a change that would expand the project scope. What should the project manager do FIRST?
- Implement the change immediately to keep the stakeholder satisfied
- Reject the change to protect the original scope
- Evaluate the impact and submit through the integrated change control process (Correct answer)
- Update the project charter to reflect the new scope
Correct answer: Evaluate the impact and submit through the integrated change control process
All scope changes must be evaluated for impact and processed through integrated change control before implementation.