A construction site operator receives a notice that their project is within a 'water quality impaired' watershed. How does this affect their CGP requirements?
-
A
They are exempt from CGP requirements in impaired watersheds
-
B
They may face more stringent effluent limits or additional BMPs
-
C
Only the MS4 operator must respond to the impairment
-
D
The CGP does not consider water quality impairments