Project Management & Resource Allocation Flashcards
7 cards from real CSM practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Project Management & Resource Allocation flashcards as text
A CSM is managing a software project where a critical vendor will deliver an API 3 weeks late. This event was identified in the risk register. What should the CSM execute first?
Answer: Implement the pre-planned risk response strategy
When a known risk occurs, the first action is to implement the pre-planned risk response, as it was designed specifically for this scenario.
In Earned Value Management, a Cost Performance Index (CPI) of 0.85 means:
Answer: The project is delivering $0.85 of value for every $1.00 spent
CPI = EV / AC; a CPI of 0.85 means only $0.85 of earned value is produced per dollar actually spent, indicating cost overrun.
Which scheduling technique allows a successor task to begin before its predecessor is fully complete, compressing the schedule?
Answer: Lead
Lead time allows a successor activity to start early, overlapping with the predecessor, which compresses the overall schedule.
A software project team is geographically distributed across three time zones. Which resource management practice has the greatest impact on productivity?
Answer: Establishing overlapping core working hours for synchronous collaboration
Defining core overlap hours ensures the distributed team has predictable windows for real-time communication, reducing blockers and hand-off delays.
A project manager calculates an Estimate at Completion (EAC) assuming future work will be performed at the current CPI. Which EAC formula is being used?
Answer: EAC = BAC / CPI
EAC = BAC / CPI is used when future performance is expected to continue at the current cost efficiency rate.
In a functional organization structure, a software project manager typically has:
Answer: Little to no formal authority; relies on influence
In a functional organization, resources report to functional managers, leaving project managers with limited formal authority and requiring influence-based leadership.
What is the PRIMARY purpose of a kickoff meeting in software project management?
Answer: To align stakeholders, clarify roles, and officially start execution
A kickoff meeting officially launches the project, ensures all stakeholders share a common understanding of goals, roles, and plans before execution begins.