CSLB Contract and Lien Laws 1 — Questions and Answers
Question 1: Under California's Mechanics' Lien Law, what is the deadline for a direct contractor to record a mechanics' lien after a Notice of Completion is filed?
- 30 days
- 60 days (Correct answer)
- 90 days
- 180 days
Correct answer: 60 days
A direct (prime) contractor must record a mechanics' lien within 60 days after a Notice of Completion is recorded by the owner.
Question 2: What is the purpose of a 'Preliminary Notice' (20-day preliminary notice) in California construction?
- To notify the owner that work will begin in 20 days
- To preserve a subcontractor's or material supplier's right to later file a mechanics' lien (Correct answer)
- To satisfy the building permit requirement
- To waive lien rights in exchange for payment
Correct answer: To preserve a subcontractor's or material supplier's right to later file a mechanics' lien
Serving a Preliminary Notice within 20 days of first providing work or materials is required for subcontractors and suppliers to preserve their mechanics' lien rights.
Question 3: In California, which party is responsible for recording a Notice of Completion after a construction project is finished?
- The general contractor
- The project architect
- The property owner (Correct answer)
- The CSLB
Correct answer: The property owner
The property owner records the Notice of Completion with the county recorder, which starts the shortened lien deadline period for contractors and suppliers.
Question 4: What is the maximum retention percentage that an owner may withhold from a contractor on a private California construction project?
- 5%
- 10% (Correct answer)
- 15%
- 20%
Correct answer: 10%
California Civil Code limits retention on private construction contracts to no more than 10% of each progress payment.
Question 5: Under California law, a mechanics' lien must be enforced by filing a lawsuit within how many days of recording the lien?
- 60 days
- 90 days (Correct answer)
- 180 days
- 365 days
Correct answer: 90 days
A mechanics' lien becomes unenforceable unless a lawsuit to foreclose the lien is filed in court within 90 days of recording.
Question 6: What is a 'Conditional Waiver and Release on Final Payment' used for in California construction?
- To certify that all subcontractors are licensed
- To release lien rights upon receiving final payment, contingent on the check clearing (Correct answer)
- To transfer project ownership to the general contractor
- To extend the warranty period on completed work
Correct answer: To release lien rights upon receiving final payment, contingent on the check clearing
A Conditional Waiver and Release on Final Payment releases lien rights only upon the actual receipt and clearance of the final payment check.
Under California's Mechanics' Lien Law, what is the deadline for a direct contractor to record a mechanics' lien after a Notice of Completion is filed?