CSI Quality Assurance Requirements 3 — Questions and Answers
Question 1: Which type of specification writing method lists acceptable products by manufacturer name and model number?
- Performance specification
- Proprietary specification (Correct answer)
- Descriptive specification
- Reference standard specification
Correct answer: Proprietary specification
A proprietary specification names specific manufacturers, products, or systems and is the most restrictive method of specifying.
Question 2: Under CSI principles, what is the purpose of a 'basis-of-design' product specified in construction documents?
- To identify the lowest-cost acceptable product
- To define the performance and quality standard that substitutions must match (Correct answer)
- To preclude any product substitutions
- To identify the owner's preferred aesthetic choice only
Correct answer: To define the performance and quality standard that substitutions must match
A basis-of-design product establishes the performance, quality, and compatibility standard that any proposed substitution must equal or exceed.
Question 3: What is the correct CSI term for the process of verifying that a product or system meets specified requirements through testing, inspection, and documentation?
- Value engineering
- Verification (Correct answer)
- Observation
- Acceptance testing
Correct answer: Verification
Verification is the CSI term for confirming through objective evidence that specified requirements have been fulfilled.
Question 4: A specification section requires 'Special Inspection' per IBC Chapter 17. Who is responsible for employing the special inspector?
- The contractor
- The general contractor's quality manager
- The owner or owner's representative (Correct answer)
- The material supplier
Correct answer: The owner or owner's representative
Per IBC Chapter 17, the owner or the registered design professional in responsible charge employs the approved special inspector.
Question 5: Which document type formally records the results of a pre-installation conference and identifies action items?
- Request for Information (RFI)
- Meeting minutes (Correct answer)
- Submittal register
- Construction change directive
Correct answer: Meeting minutes
Meeting minutes formally document the proceedings, decisions, and action items of pre-installation conferences and other project meetings.
Question 6: In quality assurance terminology, what does 'nonconformance' mean?
- Work completed ahead of schedule
- Work or materials that fail to meet specified requirements (Correct answer)
- Work that exceeds specified requirements
- Work performed by an unqualified subcontractor
Correct answer: Work or materials that fail to meet specified requirements
Nonconformance refers to any condition where materials, products, or work fail to meet the requirements established in the contract documents.
Question 7: Which QA activity requires the contractor to demonstrate installation procedures before full-scale work begins?
- Submittal review
- Field sample installation (Correct answer)
- Closeout documentation
- O&M manual preparation
Correct answer: Field sample installation
A field sample installation (or mock-up) requires the contractor to demonstrate their installation technique and achieve approval before proceeding with the full scope of work.
Which type of specification writing method lists acceptable products by manufacturer name and model number?