During a system integration project, the customer requests a feature not covered in the original scope. What process should the project manager follow?
-
A
Implement it immediately to maintain customer satisfaction
-
B
Submit a formal change request and assess impact on schedule and budget
-
C
Decline the request until the next project phase
-
D
Redirect the request to the engineering team without documentation