CSI Procurement & Bidding Procedures 2 — Questions and Answers
Question 1: Which document formally establishes the legal relationship between the owner and the contractor?
- Notice to Proceed
- Agreement Form (Correct answer)
- Bid Bond
- Certificate of Substantial Completion
Correct answer: Agreement Form
The Agreement Form (AIA A101 or similar) is the contract document that legally binds the owner and contractor.
Question 2: What is the purpose of a pre-bid conference in the procurement process?
- To award the contract to the lowest bidder
- To allow bidders to clarify ambiguities in the bidding documents (Correct answer)
- To negotiate final contract terms
- To issue the Notice to Proceed
Correct answer: To allow bidders to clarify ambiguities in the bidding documents
Pre-bid conferences give prospective bidders the opportunity to ask questions and receive clarifications about the project scope and documents.
Question 3: Under a design-build delivery method, who is responsible for both design and construction?
- The owner
- A single entity under contract to the owner (Correct answer)
- The construction manager
- The architect of record
Correct answer: A single entity under contract to the owner
In design-build, a single entity holds the contract for both design services and construction, providing the owner a single point of responsibility.
Question 4: What does the term 'responsive bid' mean in competitive bidding?
- A bid submitted before the deadline with all required documents (Correct answer)
- A bid that is the lowest price received
- A bid from a contractor with prior project experience
- A bid that includes a voluntary alternate
Correct answer: A bid submitted before the deadline with all required documents
A responsive bid complies with all procedural requirements of the bidding documents, including timely submission and required attachments.
Question 5: Which CSI MasterFormat division primarily covers bidding requirements and contracting requirements?
- Division 00 (Correct answer)
- Division 01
- Division 03
- Division 50
Correct answer: Division 00
MasterFormat Division 00 — Procurement and Contracting Requirements — contains bidding forms, agreements, bonds, and conditions of the contract.
Question 6: A 'unit price' bid requires bidders to submit pricing based on which of the following?
- A lump sum for the entire project
- Cost per measured unit of work (Correct answer)
- Percentage markup over actual costs
- Fixed fee plus reimbursable expenses
Correct answer: Cost per measured unit of work
Unit price bidding establishes a cost per unit (e.g., per cubic yard of concrete) so the final contract amount adjusts based on actual quantities.
Question 7: What is the role of a surety company in the context of construction procurement?
- It provides project financing to the owner
- It guarantees the contractor's performance and payment obligations (Correct answer)
- It inspects the work for code compliance
- It reviews and approves shop drawings
Correct answer: It guarantees the contractor's performance and payment obligations
A surety company issues bonds (bid, performance, payment) that guarantee the contractor will fulfill contractual obligations or the surety will remedy defaults.
Which document formally establishes the legal relationship between the owner and the contractor?