A project steering committee has requested weekly status reports but the project manager believes bi-weekly suffices. Who has final authority on reporting cadence?
-
A
The project manager, as operational lead
-
B
The steering committee, as the governing body
-
C
The PMO director, as methodology owner
-
D
The sponsor, as budget holder