When integrating a new industrial controller into an existing SCADA network, which step should be performed FIRST?
-
A
Begin wiring I/O modules immediately
-
B
Conduct a site survey and document existing network topology
-
C
Power on the controller and test default settings
-
D
Install software drivers on the HMI workstation