← All CSI Flashcard Decks

Procurement & Bidding Procedures Flashcards

7 cards from real CSI practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Procurement & Bidding Procedures flashcards as text
  1. What is the purpose of a 'bid withdrawal' provision in bidding documents?

    Answer: It establishes conditions under which a bidder may withdraw a bid without forfeiting bid security

    Bid withdrawal provisions define circumstances (such as clerical errors) under which a bidder may rescind their bid without losing the bid bond.

  2. Which CSI document provides a standard outline format for organizing project manuals and specification sections?

    Answer: SectionFormat

    SectionFormat provides the standard three-part format (General, Products, Execution) for organizing individual specification sections within a project manual.

  3. Under the Federal Acquisition Regulation (FAR), what threshold generally requires full and open competitive bidding for federal construction contracts?

    Answer: $150,000

    Federal construction contracts exceeding $150,000 generally require full and open competition under FAR guidelines, with sealed bidding or competitive proposals.

  4. What is the significance of the 'bid validity period' stated in the Instructions to Bidders?

    Answer: It specifies how long the bidder must honor their price after bid opening

    The bid validity period (typically 60–90 days) requires bidders to keep their prices firm for that duration while the owner evaluates bids and awards the contract.

  5. In the context of CSI procurement, what does 'responsible bidder' mean?

    Answer: A bidder who has the financial capacity, experience, and integrity to perform the work

    A responsible bidder possesses the necessary qualifications, financial strength, experience, and integrity to successfully complete the contract.

  6. What is the typical order of precedence when contract documents conflict, under AIA A201?

    Answer: Addenda supersede all other documents, then agreement, then conditions

    AIA A201 establishes that addenda (issued last) take precedence, followed by the agreement, conditions of the contract, specifications, and then drawings.

  7. Which procurement strategy is best suited when the owner wants early contractor involvement in design to improve constructability?

    Answer: Construction Manager at-Risk (CMAR)

    CMAR engages the contractor during design to provide constructability reviews, phasing input, and cost feedback before the GMP is established.