A buyer's RFP asks vendors to describe their 'implementation methodology.' What should this section demonstrate?
-
A
The number of engineers available for the project
-
B
A structured, repeatable process with milestones, roles, and risk mitigation
-
C
A flexible approach with no defined timeline
-
D
The total cost of implementation in detail