CRT Project Management for IT 2 — Questions and Answers
Question 1: A tobacco retail chain is implementing a new POS system across 12 locations. Which project management approach best suits a rollout where each location deployment provides lessons for the next?
- Waterfall with fixed phases
- Rolling wave planning with iterative rollout (Correct answer)
- Big bang deployment to all locations simultaneously
- Outsourcing the entire rollout to the POS vendor
Correct answer: Rolling wave planning with iterative rollout
Rolling wave planning allows each successive store deployment to incorporate lessons learned, reducing risk across the rollout.
Question 2: During a software upgrade project for a tobacconist's inventory system, the team discovers the vendor will discontinue support in 6 months. What risk response strategy should the project manager apply?
- Accept the risk and continue as planned
- Avoid the risk by canceling the project
- Mitigate the risk by accelerating the upgrade timeline (Correct answer)
- Transfer the risk to the vendor through contract penalties
Correct answer: Mitigate the risk by accelerating the upgrade timeline
Mitigation involves taking action to reduce the probability or impact of a risk, such as accelerating work before the deadline.
Question 3: A retail tobacconist IT project has a Schedule Performance Index (SPI) of 0.82. What does this indicate?
- The project is 18% over budget
- The project is ahead of schedule
- The project is progressing at 82% of the planned rate (Correct answer)
- The project has completed 82% of deliverables
Correct answer: The project is progressing at 82% of the planned rate
An SPI below 1.0 means the project is behind schedule, completing only 82 cents of planned work per dollar of scheduled work.
Question 4: When integrating a new age-verification software module into an existing POS system at a tobacconist shop, which document formally authorizes the project and assigns the project manager?
- Project scope statement
- Project charter (Correct answer)
- Business requirements document
- Work breakdown structure
Correct answer: Project charter
The project charter formally authorizes the project and gives the project manager authority to apply resources to project activities.
Question 5: A tobacconist chain's IT team must choose between upgrading hardware now or waiting for a new model. Which project management tool best supports this decision by comparing financial outcomes over time?
- Risk register
- Net Present Value (NPV) analysis (Correct answer)
- RACI matrix
- Gantt chart
Correct answer: Net Present Value (NPV) analysis
NPV analysis discounts future cash flows to present value, enabling objective comparison of investment timing decisions.
Question 6: During a tobacco retail IT project kickoff, the project manager conducts a stakeholder analysis. What is the PRIMARY purpose of this activity?
- To assign tasks to team members
- To identify who will be affected by the project and determine how to engage them (Correct answer)
- To estimate the project budget
- To establish the project schedule baseline
Correct answer: To identify who will be affected by the project and determine how to engage them
Stakeholder analysis identifies individuals and groups with interests in the project and helps the PM tailor communication and engagement strategies.
Question 7: A project to implement a tobacco compliance reporting system is 50% complete with a budget of $100,000 and has spent $60,000. What is the Cost Performance Index (CPI)?
- 0.60
- 0.83 (Correct answer)
- 1.20
- 1.67
Correct answer: 0.83
CPI = Earned Value / Actual Cost = $50,000 / $60,000 = 0.83, indicating the project is over budget.
A tobacco retail chain is implementing a new POS system across 12 locations.
Which project management approach best suits a rollout where each location deployment provides lessons for the next?