When presenting the risk-based engagement plan to the audit committee, the CAE should primarily communicate:
-
A
Detailed timelines for every individual audit procedure
-
B
How audit resources are allocated based on identified risk priorities
-
C
Results of all previously completed audit engagements
-
D
Approval requests for each specific audit test step