What is the primary purpose of a Weekly Maintenance Schedule (WMS)?
-
A
To document all equipment failures that occurred in the previous week
-
B
To assign specific work orders to specific crews and time slots for the coming week
-
C
To calculate the total maintenance budget for the month
-
D
To track spare parts consumption across all departments