A plant manager wants to justify a $200,000 vibration monitoring program to the CFO. Which metric best expresses the program's value in financial terms?
-
A
Percentage of PM work orders completed on time
-
B
Number of sensors installed per asset
-
C
Mean time to repair for monitored assets
-
D
Return on investment based on avoided downtime and repair costs