Which maintenance strategy is BEST suited for components where failure consequences are safety-critical and failure modes are detectable before function loss?
Answer: Condition-based maintenance
Condition-based maintenance monitors detectable degradation signals to intervene before safety-critical failures occur.
In a risk matrix, a hazard rated 'Catastrophic' severity with 'Improbable' likelihood is typically classified as:
Answer: ALARP region risk
Catastrophic severity with low probability typically falls in the ALARP (As Low As Reasonably Practicable) region requiring justification to accept.
The P-F interval in predictive maintenance refers to the time between:
Answer: Potential failure detection and functional failure
The P-F interval is the time from when a potential failure becomes detectable to when functional failure occurs.
Which risk reduction technique involves adding redundant systems to reduce the probability of overall system failure?
Answer: Fault tolerance
Fault tolerance uses redundancy so that individual component failures do not cause system-level failure.
A Bow-Tie diagram in risk management combines which two analysis techniques?
Answer: Fault Tree Analysis and Event Tree Analysis
A Bow-Tie diagram uses a Fault Tree on the left (causes leading to a hazard) and an Event Tree on the right (consequences).
When applying RCM (Reliability-Centered Maintenance), the first question to ask about each function is:
Answer: What is the item's function?
RCM always begins by defining what functions the asset is required to perform in its operating context.
Which maintenance tactic is most appropriate for a component with an Infant Mortality failure pattern (high early failure rate)?
Answer: Burn-in testing before installation
Burn-in or run-in testing screens out early failures before installation, reducing field failures from infant mortality.