  1. Which type of control chart is most appropriate for monitoring the proportion of defective items in a variable-size sample?

    Answer: p-chart

    The p-chart monitors the proportion (fraction) defective and accommodates variable sample sizes.

  2. In acceptance sampling, what does the Operating Characteristic (OC) curve depict?

    Answer: The probability of acceptance versus the lot defect rate

    The OC curve plots the probability of accepting a lot against its true defect rate, showing discrimination power.

  3. A process has a Cpk of 0.85. What does this indicate?

    Answer: The process is not centered and is producing defects beyond specification limits

    Cpk below 1.0 indicates the process is not capable; it is producing output outside at least one specification limit.

  4. Which quality tool is specifically designed to determine which input variables most significantly affect an output variable?

    Answer: Design of Experiments (DOE)

    DOE systematically varies input factors to quantify their individual and combined effects on process outputs.

  5. What is the purpose of a gage R&R (Repeatability and Reproducibility) study?

    Answer: To quantify measurement system variation relative to process variation

    Gage R&R assesses how much of the observed variation is due to the measurement system itself versus the actual process.

  6. Under MIL-STD-1916, what sampling philosophy replaced AQL-based sampling?

    Answer: Zero Acceptance Number (c=0) sampling

    MIL-STD-1916 promotes zero acceptance number plans, emphasizing defect prevention over detection.

  7. When a control chart shows a run of 8 consecutive points on one side of the centerline, this indicates:

    Answer: A non-random pattern suggesting a process shift

    Eight consecutive points on one side of the centerline is a Western Electric rule violation signaling a process mean shift.