CRC Project Planning & Scheduling 2 — Questions and Answers
Question 1: Which scheduling technique uses arrows to represent activities and nodes to represent events?
- Critical Path Method (CPM)
- Arrow Diagramming Method (ADM) (Correct answer)
- Precedence Diagramming Method (PDM)
- Program Evaluation Review Technique (PERT)
Correct answer: Arrow Diagramming Method (ADM)
Arrow Diagramming Method (ADM) uses arrows for activities and nodes for events, also called Activity-on-Arrow (AOA).
Question 2: A residential contractor discovers soil conditions require deeper footings than planned. Which document should be issued first?
- Change order (Correct answer)
- RFI (Request for Information)
- Punch list
- Submittal
Correct answer: Change order
A change order formally documents and authorizes scope, cost, and schedule changes when unforeseen conditions alter the original plan.
Question 3: What is the primary purpose of a baseline schedule in residential construction?
- To list all subcontractors on the project
- To serve as the original approved plan against which progress is measured (Correct answer)
- To document material delivery dates only
- To satisfy local permit office requirements
Correct answer: To serve as the original approved plan against which progress is measured
The baseline schedule is the approved original plan used to measure project performance and identify variances.
Question 4: A homeowner requests an addition that was not in the original contract. How should a contractor handle this?
- Proceed immediately to maintain client goodwill
- Issue a written change order before starting work (Correct answer)
- Note it in the job log and address later
- Deny the request to avoid scope creep
Correct answer: Issue a written change order before starting work
A written change order must be executed before additional work begins to protect both the contractor and owner legally and financially.
Question 5: In a Gantt chart, what do overlapping bars typically indicate?
- Activities that cannot start until a prior one finishes
- Tasks that are behind schedule
- Activities occurring simultaneously (parallel work) (Correct answer)
- Budget overruns on those tasks
Correct answer: Activities occurring simultaneously (parallel work)
Overlapping bars on a Gantt chart show that two or more tasks are scheduled to occur at the same time.
Question 6: Which resource leveling strategy extends the project duration to avoid resource conflicts?
- Crashing
- Fast-tracking
- Resource smoothing
- Resource leveling (Correct answer)
Correct answer: Resource leveling
Resource leveling adjusts the schedule, often extending the end date, to resolve over-allocation of resources.
Question 7: A framing crew finishes 3 days early. Which scheduling concept describes the time saved that can benefit successor tasks?
- Total float
- Free float (Correct answer)
- Negative lag
- Lead time
Correct answer: Free float
Free float is the amount of time an activity can be delayed without delaying its immediate successor activities.
Which scheduling technique uses arrows to represent activities and nodes to represent events?